News

Anaerobic Digestion Plants

April 2017

Latest News

Construction is substantially complete on all 4no of 250Kw sites and 1no of 200KW sites. The CHP units on each plant have been installed and were successfully commissioned in time to make the plants eligible for ROC accreditation before the 31st March 2017 deadline. Each plant now has its digester tank seeded and being heated, with the biological process in the ramp up phase aiming for full biogas output.

The New Mill Farm AD Plant, a 2MW electricity to grid plant and our first project for funder Iona, has been successfully commissioned and handed over to the client.